By Yusuf Bello
Electricity supply has been disrupted in parts of Port Harcourt and its environs following a labour-related incident at the Afam IV Gas Power Station.
The Transmission Company of Nigeria (TCN), in a statement on Tuesday, said the disruption began on Monday, September 28, 2026, after members of the National Union of Electricity Employees (NUEE), Rivers State Chapter, opened the Afam–Alaoji 330kV Transmission Line 2 at the Alaoji 330kV Transmission Substation.
TCN said the action was connected to an ongoing labour dispute between the management of Afam IV Gas Power Station and NUEE.
According to the company, the development caused the 150MVA 330/132kV inter-bus transformer at Afam IV to trip, disrupting bulk electricity transmission to parts of Port Harcourt and neighbouring areas.
The affected transmission facilities include the Port Harcourt Town 132kV Transmission Substation, Elelenwo 132kV Transmission Substation and the 60MVA 132/33kV transformer at the Port Harcourt Mains 132kV Transmission Substation.
TCN said it was engaging relevant stakeholders, including the Nigerian Independent System Operator (NISO), to restore the affected facilities as soon as conditions permit safe restoration.
The transmission company apologised to electricity consumers in the affected areas for the inconvenience, assuring that further updates would be provided as the situation develops.